The fibreglass pool restoration process takes between 7 and 14 days, considering conventional pool conditions:


1. Pool Draining

The first step involves completely draining the pool to remove all water, allowing work to be done on the surfaces and internal layers.


2. Tent Structure Setup

A tent structure is set up around the pool to contain the dust and protect the surrounding environment from any debris generated during sanding and other work processes. (If the pool site does not offer safe conditions for erecting the wooden structure, conventional dust containment using tarps and ropes will be used).


3. Cleaning and Surface Regularization

Next, a deep cleaning of the pool surface is carried out to remove dirt, residues, and contaminants. After cleaning, the surface is sanded to prepare it for the new coatings. If there is osmosis or cracks, these imperfections are addressed by removing the osmosis and/or repairing the cracks. If necessary, bog is applied to smooth and regularize the surface.


4. Resin Sealing

For concrete pools, a resin sealing is applied to ensure a strong and adhesive base for the fiberglass layer.


5. Fibreglass Lamination

The next step involves fibreglass lamination, where multiple layers of fibreglass mat are applied to the pool for durability and structural strength.


6. Sanding and Resin Application

Once the fiberglass has dried, the surface is sanded again, followed by the application of another layer of resin. This step ensures better durability and a smoother, more polished finish.


7. Waterline Tiles and Additional Work

After the resin has cured, waterline tiles are applied, and any other extra services requested (e.g., coping renovation, paving, feature walls, etc.) are completed during this stage.


8. Application of AquaGuard Paint

Two coats of AquaGuard waterproof paint are applied to provide the final layer of protection and enhance the overall finish.


9. Curing Time

After completing the coating, the pool needs to cure for 7 days before it can be refilled. During this time, all layers must fully harden and settle. It is necessary to keep the pool completely dry during this period. For greater convenience, we leave our tent set up during this period.


10. Final Touches

Before the pool is refilled, final touches such as the installation of jets, pool lights, and the valve system are completed.


11. Water Treatment

After the pool is filled with water, you need to wait for another 7 days before performing any chemical water treatments to ensure proper balance and pool maintenance.


Note on Variability:

The total restoration time may vary depending on factors such as:

  • Pool size and type (e.g., fiberglass, concrete)

  • The condition of the pool (extent of damage, wear, cracks)

  • Additional services requested (e.g., coping, paving, feature walls)

  • Weather conditions

  • Current pool condition and amount of work needed


If you would like to know how much a fiberglass resurfacing costs, contact us for a free consultation to assess your pool's specific needs.






 
 
 